Axpo and local partner Riienergie opened their first hydrogen production plant, co-located with the Reichenau hydro power plant, at the end of April 2024. The 2.5-megawatt plant produces up to 350 tonnes of green hydrogen per year.
Altenso installed and commissioned the PCU in March 2024.
Project Figures
Amount MVPS
1 x 40‘ MVPS station
PCU Capacity
2.5 MW
Electrolyzer
PEM
SMA System Technology
Our rectifiers are manufactured in a serial mass production in Niestetal (Germany). We keep highest production standards and deliver worldwide even to very remote and secluded locations.