The project includes a 27.4 MW solar farm, another 10.7 MW solar farm, a 11.2 MW / 5.4 MWh Leinster BESS, and interconnecting transmission infrastructure. The system solutions save over 540,000 tonnes of CO2, powering the two nickel mines from BHP.
Project Figures
Power
38.2 MW
Components
4 x SCS 2900 / 10 x SC 4200 UP
Monitoring
SMA Power Plant Controller
Battery capacity
5.4 MWh
Role
Integrator
Application
Mining Electrification
SMA System Technology
Our system solutions are manufactured in a serial mass production in Niestetal (Germany). We keep highest production standards and deliver worldwide even to very remote and secluded locations.